The Night Trucks Leaving Woody Creek Stop Before Thanksgiving

November 19, 2026

The trucks leaving Woody Creek after dark this month are carrying part of next year's runway. Since Monday, Nov. 9, crews have been hauling construction material from the Vagneur Gravel Pit in Woody Creek to Aspen/Pitkin County Airport, stockpiling it for the 2027 runway reconstruction. The trucks run from 7 p.m. to 4 a.m., Monday nights through early Saturday mornings, on Smith Hill Way and Highway 82.

Under Pitkin County's schedule, the second and final week runs Nov. 16 to 21. As this post goes up on Thursday, two nights of hauling are left. The last loads are due early Saturday morning, Nov. 21, and two days later, on Monday, Nov. 23, RFTA's free Woody Creek bus comes back for the winter.

That timing was planned. Commissioners wrote the end date into the approval, and this year's hauling was cut to a window that closes before the holiday. The nightly cap on truckloads went up in the same approval.

Why the Trucks Run at Night

Pitkin County's Nov. 6 notice gives the reason in one line. "Stockpiling materials ahead of construction will help reduce daytime truck traffic and keep the runway reconstruction project on schedule." The airport's construction updates make the same point. Moving the material now cuts down how much hauling has to happen during daytime traffic hours.

The runway work itself is scheduled. The airport is set to close to all aircraft at 11 p.m. on Sunday, April 4, 2027, and is scheduled to reopen at 7 p.m. on Friday, Nov. 19, 2027. Groundwork has already started. This fall the airport's updates described crews getting the batch plant area ready for next year's construction and testing the materials that will go into the runway. Owl Creek Road reopened in both directions on its new alignment after paving finished Oct. 31, and the Owl Creek Trail moved to its permanent route.

The gravel coming out of Woody Creek feeds that same project. More of it moved now means fewer loaded trucks on Highway 82 at midday next spring.

The Permit Behind the Overnight Hours

The pit is not normally a nighttime operation at this scale. The Aspen Daily News reported on Oct. 17 that Elam Construction had won initial approval from the Board of County Commissioners to expand night hauling at its Woody Creek gravel pit. The emergency resolution raised the limit to 130 truckloads a night from the previously permitted 40. The same report said Elam had wanted to start on Oct. 12 and run 32 nights in total, against the 10 nights it was already permitted.

In mid-October the airport described a longer window from Oct. 19 to Nov. 24, running from 7 p.m. to 7 a.m. On Nov. 4, Citizen Portal reported that commissioners approved an emergency confirmatory amendment to a 2009 development permit. They adjusted the dates because night hauling had not yet begun, and made sure the stop date fell before Thanksgiving. The county's Nov. 6 notice set the final windows.

Earlier permit, as reported Plan described in mid-October Schedule announced Nov. 6
Truckloads per night Up to 40 Up to 130 Up to 130
Nights 10 permitted 32 planned Five a week, Nov. 9–14 and Nov. 16–21
Hours Not specified 7 p.m. to 7 a.m. 7 p.m. to 4 a.m.
Final morning Not specified Nov. 24 Nov. 21

On the final schedule, trucks are off the road three hours earlier each morning than in the October plan, and the run ends three days sooner. The county notes that the schedule can still shift with weather and operating conditions.

What the Pit Is Not Doing After Dark

The night permission covers less than the truck counts might suggest. Pitkin County limits overnight work at the gravel pit to loading and hauling, with no crushing and no asphalt production. Drivers have been told to keep speeds down and not to use engine brakes. If weather or road conditions make night driving unsafe, hauling stops.

The Aspen Daily News reported that the pit's existing rules on noise, air quality and traffic control remain in force alongside the night approval, and so does the requirement to notify nearby residents. The airport's update also said neighbors would get advance notice of operations.

On Smith Hill Way and Highway 82, the county says to expect more trucks and possible noise during those hours, and asks drivers to take care around construction vehicles. The Aspen Times carried the same schedule and confirmed that operations run through Nov. 21.

The Monday After the Last Load

Once the final trucks finish early Saturday, Woody Creek's next routine comes back. RFTA's fall schedule, which ran from Sept. 21 through Nov. 22, paused Woody Creek service for the off-season. Winter service starts Monday, Nov. 23, runs through April 18, 2027, and brings back the WC route.

RFTA's posted winter WC timetable lists six stops: Phillips Trailer Park, River Bend, Woody Creek Tavern, WJ Ranch, Juniper Hill Road/Smith Way and Brush Creek Park & Ride. The service is free. Buses run hourly every day in a morning block and an evening block, with no service in the middle of the day.

Direction Morning departures Evening departures
From Phillips Trailer Park toward Brush Creek 6:08, 7:08, 8:08 and 9:08 a.m. Hourly from 5:08 p.m. to 12:08 a.m.
From Brush Creek Park & Ride toward Woody Creek 6:30, 7:30, 8:30 and 9:30 a.m. Hourly from 4:30 p.m. to 12:30 a.m.

Heading toward Brush Creek, the Woody Creek Tavern stop comes 10 minutes after Phillips Trailer Park, and the bus reaches Brush Creek 16 minutes after leaving. Coming back, the Tavern is four minutes out of Brush Creek. The Tavern's own site lists service from 11 a.m. until close, seven days a week, along with a Fall '26 all-day menu.

The WC bus does not go into Aspen. Riders change at Brush Creek Park & Ride, where Brush Creek Road meets Highway 82 and parking is free. The Snowmass–Aspen route stops at both Rubey Park Transit Center and AABC Airport. Some of its trips end at Brush Creek and others go on to Aspen, so RFTA asks riders to check the destination sign before boarding.

What 2027 Asks of the Same Road

This month's stockpile does not finish the job. The Aspen Daily News reported that Elam told commissioners it would come back with another request for 2027. That request goes back to the same board of commissioners that set this fall's caps and end date.

The airport closure also changes how the valley moves. The airport's guide for travel during the closure points riders to Brush Creek Park & Ride for local transit. The airport has said it will release more local ground transportation details before the closure begins. Brush Creek is also where WC riders already transfer, so the Woody Creek bus connects at the same hub the airport is directing travelers to.

To follow what comes next, the county recommends the airport's construction updates page and its Frequent Flyer Updates email list.

The 2027 runway work will affect property in Woody Creek, from daytime traffic to the timing of a sale or a renovation. If you want to talk through how that schedule bears on a home here, Saslove and Warwick know this end of the valley well and would be glad to help.